º£½ÇÊÓÆµ

Oops.

Our website is temporarily unavailable in your location.

We are working hard to get it back online.

PRIVACY
Tech

Software update that could have prevented huge power cut was just days away

Siemens Gamesa system improvement was just five days away from installation on Orsted's Hornsea One world-leading wind farm

A software update that could have prevented the major power cut in August was just days away from installation on Hornsea One offshore wind farm, the official report into what happened has revealed.

A software update that could have kept Hornsea One operational through the freak incidents that lead to last August’s huge power cut - potentially avoiding it altogether - was just days away from installation, it has emerged.

Orsted’s world-leading offshore wind farm was in the process of demonstrating compliance as a new generator when lightning struck a transmission cable in Cambridgeshire, sparking a chain of events that led to one million people losing power.

It left trains incapacitated across the rail network, while four hospitals had to revert to emergency back-up systems and Newcastle Airport was forced to close. It emerged on Friday the company has agreed to pay £4.5 million into Ofgem’s redress fund as part of a £10.5 million industry contribution following the publication of the official reports.

Set to be fully commissioned early this year, the Grimsby-operated 1,218MW farm was knocked out alongside RWE’s gas-fired plant at Little Barford on the early evening of August 9. Together they exceeded the back-up available, leading to strategic disconnections to manage the loss across the grid.

The worst power cut for a decade is under investigation, with the link, systems and operators between the lights going out and generators Hornsea One offshore wind farm and Little Barford gas-fired power station being looked at.(Image: PA / Orsted / Google Maps)

 

Hornsea, then entering the final two months of the installation campaign, had two of the three 400MW units that feed from the giant arrays off the Humber approaches generating at capacity due to the windy conditions, with the third unit – in which turbines were still being installed from the pre-assembly port of Hull – permitted to export 20 per cent.

It has been common practice for the farms to be ramped up as they are built out, with the clean electricity contributing to the huge increase in renewables and subsequent reduction of coal as a fuel source from the system, while money earned helps cover some of the ongoing construction costs.

 

When the lightning strike struck, it caused a voltage fluctuation across the transmission network, which prompted a response from Hornsea One in an attempt to correct it. Initially aiding, the control system then “responded unexpectedly” which ultimately led to Hornsea One offshore voltage being depressed to a point where protection systems were activated on the two units.