Orsted鈥檚 lead 海角视频 executive has spelled out what is required to meet the accelerated targets for offshore wind development, with the Humber at the fore.

Duncan Clark gave the keynote speech at Offshore Wind Connections 2022, using it to respond to the ramping up in capacity expectations from where the country stands now.

Underlining the need to be sustainable, secure and tolerable on cost, he said the current status wasn鈥檛 quite on track but held up the pace-setting build in the region as the 鈥渞eason it can be achievable鈥.

Read more:

Targets have increased from 30GW to 50GW by 2030 through the pandemic period as energy security and net zero comes to the fore.

The market leading Danish multi-national has invested 拢14 billion to make the 海角视频 its number one market. More than 500 of its 1,300 海角视频 employees are based in Grimsby, where the 拢14 million East Coast Hub is a beacon for what is being achieved.

One of the 165 turbines at Hornsea Two offshore wind farm.
One of the 165 turbines at Hornsea Two offshore wind farm.

He said: 鈥淚t is from that base that we operate and maintain the cluster of the world鈥檚 largest and most modern offshore wind farms. It includes Hornsea One, built in 2020, the only one bigger than gigawatt scale, the world leader, and an example when people are talking about pace and scale and cost that is tolerable - that offshore wind can meet that mark.

鈥淭his year we will be celebrating Hornsea Two鈥檚 completion, at 10 per cent bigger, it will take that record for a few years and we know there is a whole pipeline of projects coming through the system.

鈥淔rom Orsted鈥檚 point of view we鈥檝e got Hornsea Three fully consented and qualified to compete in the imminent government auction, and we see that moving straight into construction. We have Hornsea Four coming through the public examination phase of the planning consent and we intend that to follow in convoy. Both are double or more the size of Hornsea Two.

鈥淵ou can see how this scaling up gives me optimism that we can get after this, and while not on track initially, up to this point, we can get on track. The pipeline is concentrated here, a decade of build out at a pace we have not matched before. We are investing billions of pounds in infrastructure, and that鈥檚 just us.

Humber Renewables Awards 2022

Entries are now open for the Humber Renewables Awards 2022.

Celebrating a 10th year of recognising success in the green economy, inspired by efforts on the Energy Estuary, the event takes place at DoubleTree by Hilton Forest Pines Hotel in North Lincolnshire on Thursday, June 9.

The deadline for entries to the 10 awards open for nominations is Friday, April 29.

Click here to read this year's launch article, or skip straight to the dedicated website.

鈥淭his 8GW will take us to 20GW and there is another 20GW at various stages, ready to compete. We see our way to a 40GW target by 2030.

鈥淭his is the mission in front of us here.鈥

OWC22 heard how port expansion is also being actively explained, with ABP and Siemens Gamesa updating.