º£½ÇÊÓÆµ

Oops.

Our website is temporarily unavailable in your location.

We are working hard to get it back online.

PRIVACY
Manufacturing

Major gas pipeline tunnel dig completes 18-month sub-Humber crossing

Breakthrough achieved on 5km long incredible feat of engineering and infrastructure development 

A complete tunnel section. At the far end, operatives are carrying out works with the tunnel boring machine further in front of them. The bagging above is the air duct, which feed fresh air to the tunnel. The pipes and cables on the left are electric cables, free washer pipes, grout pipes, slurry input and extraction pipes.(Image: National Grid)

An incredible 18-month tunnel bore 30 metres below the River Humber has been completed.

National Grid is behind the huge infrastructure project to house a replacement gas pipeline, with 160-metre long machine ‘Mary’ breaking through into a specially constructed shaft at Paull on the North Bank.

She left Goxhill on the South Bank back in April  2018, and since then has excavated 160,000 tonnes of material - mostly chalk – creating a tunnel nearly 5km long and more than 3.5m in diameter.

A team of 40 engineers working around the clock on the £100 million project, representing National Grid and its joint venture contractors Skanska, PORR Bau GmbH and A. Hak.

Steve Ellison, lead project manager for capital delivery at National Grid, said: “Completing the tunnel beneath the Humber is a major milestone for the project team and our project partners.  It’s the first time a tunnel has been constructed beneath the River Humber and a fantastic achievement for everyone involved.

“Over the next few weeks we’ll be dismantling the tunnel boring machine and lifting her out of the ground in sections, ready to be transported back to Germany, where as much as possible will be refurbished and renewed to get her ready for her next tunnelling job.”

It is no mean feat in itself as she is 11 double decker buses long.

“The next steps for us here under the Humber involve clearing the pipes, cables and ancillary equipment that has been servicing the tunnel boring machine and preparing for the world record breaking pipeline installation early next year,” Mr Ellison added.