Manufacturing

Delays and costs mount at Tricoya º£½ÇÊÓÆµ Hull plant with production unlikely this year

Costs have spiralled from £59m to a potential £96m with site suffering from ongoing construction challenges

Accsys' Tricoya º£½ÇÊÓÆµ production plant at Saltend Chemicals Park, Hull.(Image: Accsys)

An emerging new construction materials manufacturing plant at Saltend has been hit by further delays and additional costs, while the price of gas has put future profitability into question.

Production at Tricoya º£½ÇÊÓÆµ Ltd - where a wood composite innovation has been touted as a significant development in the industry - is now unlikely this year, according to bosses, as partners in the consortium try to agree on new funding. Costs have soared from an original £59 million to a potential £96 million.

Early summer had seen commissioning commence at the plant, but “continued construction challenges” were experienced, with changes to the original work required.

Read more: £341m buy-out of Triton Power by SSE Thermal and Equinor completes

The details emerged in an update to the City from Accsys Technologies Plc, the business leading the joint venture project. It follows initial structural engineering issues that initiated delays and led to the loss of the lead contractor, Engie Fabricom, from the project, with Accsys taking the responsibility in-house.

The Anglo-Dutch listed firm had already ploughed further investment in, and now it is looking at a third tranche, with up to £6.9 million agreed.

A total of 30 jobs are anticipated once operational, which had first been planned for mid-2019 when announced in early 2017.

Accsys, a BP-backed legacy, taken on by Ineos as part of the acquisition of the chemicals business , has a sister plant is operational in Arnhem, Netherlands, with a third plant being built in the US.