º£½ÇÊÓÆµ

Oops.

Our website is temporarily unavailable in your location.

We are working hard to get it back online.

PRIVACY
Enterprise

Anglo American provides update on slowed down work at Woodsmith Mine

Anglo American says there has been progress despite scaling down of investment in the site and pause on some activities which sparked hundreds of job losses on Teesside

An aerial view of Woodsmith Mine (Image: Anglo American)

Mining giant Anglo American has reaffirmed that its halted Woodsmith Project could resume within two years.

Executives at the FTSE100 global company say progress has been made on the multibillion-pound scheme, despite significantly reduced investment in the site and suspension of some activities which triggered hundreds of redundancies.

Work to construct the 37km long tunnel that will transport polyhalite fertiliser from the mine site near Whitby to Redcar, where it will be processed and exported, has proceeded at a reduced rate with approximately 29.6km of the tunnel now excavated.

There has also reportedly been substantial advancement on the sinking of a service shaft at the mine site.

The first half of this year has witnessed workers drilling through sandstone rock formations, alongside grouting and installation of water-tight lining, reports .

Meanwhile sinking of the mine's main production shaft has been suspended for more than a year.

Anglo said it remains concentrated on maintaining the "exceptional, long-term value" of the mine, and has highlighted three criteria that must be satisfied before it can receive approval for full development by its board.

The conditions include completion of a feasibility study utilising information from the sandstone rock strata; securing a "syndication" partner on the project and reduction of debt on the group's balance sheet. In an update to investors, it said: "The transition to slowdown status was completed in Q1 2025 with activities now focused on critical value-adding works to de-risk the overall project schedule, preserve progress in areas that are in care and maintenance, and further optimise certain scopes of the project to be ready for ramp-up when conditions allow."