º£½ÇÊÓÆµ

Oops.

Our website is temporarily unavailable in your location.

We are working hard to get it back online.

PRIVACY
Economic Development

HS2 risk and complexity 'were underestimated' says spending watchdog

New report published today by the National Audit Office says the costs of the high-speed rail project remain uncertain and could yet change

How HS2's station in Birmingham could look

A scathing new report published today into HS2 says it is over budget and running late because the Government underestimated the project's complexity and risk.

It adds that significant challenges to completing the programme and delivering value for taxpayers and passengers remain.

The new report, called 'High Speed Two: A progress update', has been published by parliamentary spending watchdog the National Audit Office (NAO) although many of its findings were revealed last year by HS2.

It comes just days after the results of the review into the project by its former chairman Douglas Oakervee were leaked to the media ahead of its official publication in the coming weeks.

According to the leak, the project should continue but certain elements would be looked at again.

Phase one of HS2 is due to run between Birmingham and London and be open by 2031 while a second phase, between Birmingham and the North West, East Midlands and Yorkshire will complete by 2040.

Both of those completion dates are revised from initial projections after it was confirmed last summer that phase one would open up to five years later than planned and phase two seven years later.

The NAO's new report says the Department for Transport's (DfT) latest estimate of the cost of HS2 is between £65 billion and £88 billion based on 2015 prices, between 17 per cent and 58 per cent over available funding, with the NAO warning that "costs are uncertain and could change".